| Estimate No. | 1001 |
| Prepared Date | October 17, 2026 |
| Expiration Date | November 16, 2026 |
Your Company
Your Client
123 Street Name, Ste 987
Sampletown, XY 50001
A full remodel of the kitchen in its existing layout: new cabinets, quartz countertops, backsplash, luxury vinyl plank flooring, recessed and pendant lighting, and paint, with all permits, inspections, and cleanup. Appliances are supplied by you and installed by us.
| Description | Qty | Total Price | ||
|---|---|---|---|---|
| Preparation and demolition | ||||
|
Floor and room protection and dust barriers |
1 | $850.00 | ||
|
Demolition of cabinets, countertops, and flooring |
1 | $3,200.00 | ||
| Framing and drywall | ||||
|
Framing repairs and cabinet blocking |
1 | $1,400.00 | ||
|
Drywall patch, tape, and finish |
1 | $2,100.00 | ||
| Electrical | ||||
|
Electrical rough-in and six new circuits |
1 | $4,800.00 | ||
|
Recessed lights (installed) |
8 | $1,480.00 | ||
| Plumbing | ||||
|
Plumbing rough-in and fixture setting |
1 | $3,600.00 | ||
| Cabinets and countertops | ||||
|
Cabinet allowance (supply) |
1 | $18,000.00 | ||
|
Cabinet installation and hardware |
1 | $3,400.00 | ||
|
Countertop allowance (quartz, fabricated and installed) |
1 | $7,500.00 | ||
| Tile and flooring | ||||
|
Backsplash tile allowance (materials) |
1 | $900.00 | ||
|
Backsplash tile installation (sq ft) |
45 | $1,260.00 | ||
|
Luxury vinyl plank flooring, installed (sq ft) |
220 | $2,420.00 | ||
| Fixtures and finishes | ||||
|
Fixture allowance (sink, faucet, pendants) |
1 | $2,200.00 | ||
|
Paint, walls and ceiling |
1 | $1,900.00 | ||
|
Appliance installation (owner supplied) |
1 | $650.00 | ||
| Permits and closeout | ||||
|
Building permit and inspections |
1 | $1,200.00 | ||
|
Dumpster, final cleanup, and haul-off |
1 | $1,350.00 | ||
|
Project management and supervision |
1 | $4,290.00 | ||
| Total Due | USD $62,500.00 | |||
This estimate is valid for 30 days. Allowances are budgets for your selections. If a selection costs more, the difference plus 10% is added by change order before ordering, and if it costs less, the difference is credited to you.
Not included: appliances, work outside the kitchen, removal of asbestos, lead paint, or mold if found, and any electrical service panel upgrade the utility or inspector requires. We’ll confirm the scope, schedule, and payments in a proposal and contract.